Campus backbone across a five-building business park

A phased structured cabling package delivered building by building while the first tenants were already occupying, without moving the handover date

At a glanceReal Estate & ConstructionNew CairoHandover 2025Structured CablingProject Management & Consulting
Campus backbone across a five-building business park
ClientA Grade A office development in New Cairo
SectorReal Estate & Construction
LocationNew Cairo
Handover2025

The challenge

The first tenant moved in before the last shell was closedThree buildings were handing over on different dates. Anything designed only for the finished campus would have failed the first two years of the development's life.
Containment was decided before we were invitedRoutes had been set by the MEP package months earlier. We had to work the backbone through what already existed rather than what we would have drawn.
The programme had already absorbed one delayTechnology was the last package on site and the first candidate for compression.

What we delivered

Structured CablingOS2 fibre backbone between all five buildings, Cat6A horizontal to every floor, designed for occupied capacity rather than day one
Project Management & ConsultingHeld the technology scope across the campus and coordinated the sequence with the main contractor

Worked to TIA-568, ISO/IEC 11801, IEC 60364.

The numbers

2,400outlets tested and certified
Data outlets installed and certified2,400
Certification pass rate at first test99.1%
Copper installed68 km, Cat6A
Fibre backbone installed4.2 km, OS2
Floors covered23 across 5 buildings
Manufacturer warranty secured25 years
Mobilisation to final handover31 weeks, phased
Delivered against programme9 days ahead

The outcome

Each building handed over on its own date with a complete test pack, so the operator took possession with evidence rather than assurances. The developer let floor space in two buildings while the third was still in fit-out.

Documentation handed over

  • As-built drawings per building
  • Certification results for all 2,400 points
  • Labelling schedule
  • O&M manuals
  • Warranty registration

Related

Other projects

Have a site like this one?

Tell us what has to run in it and when it has to be live. We will come back with a scope and a programme, not a brochure

Message an engineer on WhatsApp