At a glanceTelecomGreater Cairo and the DeltaHandover 2025Structured CablingIT Power SolutionsMaintenance & Managed Services

ClientA licensed telecom operator
SectorTelecom
LocationGreater Cairo and the Delta
Handover2025
The challenge
Eighty-four sites, eighty-four different historiesTwo decades of incremental work meant no two equipment rooms were cabled the same way. Fault-finding took a senior engineer and a torch rather than a drawing.
The availability commitment was already soldThe operator had committed a figure to enterprise customers. Every hour of work had to be planned backwards from that number.
Access was the real programme riskPermits, escorts, landlord approval on rooftops and shared sites. On several nodes we had four hours a night, twice a week, and no more.
What we delivered
Structured CablingOS2 fibre and Cat6A to a single build standard across every site, terminated, tested and labelled identically
IT Power SolutionsDC power paths and battery strings audited, replaced where failed, and load tested at every site
Maintenance & Managed ServicesA preventive schedule written for a distributed estate rather than for one building
Worked to TIA-568, ISO/IEC 11801, IEC 62040, ETSI EN 300 019.
The numbers
84sites built to one standard
| Sites delivered | 84 |
| Fibre installed | 19.4 km, OS2 |
| Copper installed | 31 km, Cat6A |
| Ports terminated and certified | 6,180 |
| Certification pass rate at first test | 98.6% |
| Battery strings replaced | 47 of 84 sites |
| Autonomy achieved at full load | 4 hours, load tested per site |
| Service-affecting events during delivery | 0 |
| Programme duration | 14 months, night works |
The outcome
Site eighty-four now looks like site one, on paper and in the rack. A fault that used to need a senior engineer on site is diagnosed from the records, and the operator can hand a new contractor a build standard instead of an explanation.
Documentation handed over
- As-built drawings per site
- Certification results for all 6,180 ports
- Battery condition baseline per site
- Labelling standard
- Preventive maintenance schedule
Related
Other projects
2025Real Estate & Construction
Campus backbone across a five-building business park
A Grade A office development in New Cairo
2,400outlets tested and certified
2024Banking & Financial Services
Primary data centre build for a tier-one bank
A tier-one Egyptian bank
99.98%measured availability since handover
2025Healthcare
Six hospital sites brought onto one surveillance platform
A private healthcare group operating across Greater Cairo
640cameras on a single operator position
Have a site like this one?
Tell us what has to run in it and when it has to be live. We will come back with a scope and a programme, not a brochure