Comms rooms and access control for a government authority campus

A three-building authority campus cabled, secured and documented against the tender specification as written, and accepted at first inspection.

At a glanceGovernment & Public SectorNew Administrative CapitalHandover 2024Structured CablingPhysical Security & SurveillanceProject Management & Consulting
Comms rooms and access control for a government authority campus
ClientA national regulatory authority
SectorGovernment & Public Sector
LocationNew Administrative Capital
Handover2024

The challenge

The specification was the contractTwo clauses were technically unachievable as drafted. We raised both in writing before pricing rather than as a variation halfway through.
Acceptance ran through three partiesConsultant, authority engineering and a separate security directorate, each with their own witness testing requirements.
The buildings will be held for decadesWhoever maintains this campus in 2044 will be working from the pack we hand over, not from anyone who built it.

What we delivered

Structured CablingCat6A horizontal and OS2 backbone across three buildings, certified point by point
Physical Security & SurveillanceAccess control and video to the stated retention policy, integrated on one platform
Project Management & ConsultingHeld the technology scope through witness testing and formal acceptance

Worked to TIA-568, ISO/IEC 11801, NFPA 72, EN 60839.

The numbers

0findings at final inspection
Data outlets installed and certified1,850
Certification pass rate at first test99.4%
Buildings covered3
Access controlled doors186
Cameras installed240
Video retention delivered180 days
Witness test sessions passed11 of 11
Findings raised at final inspection0
Award to formal acceptance11 months

The outcome

The campus was accepted at first inspection with no findings raised against the technology packages, which released the authority handover milestone on its original date.

Documentation handed over

  • As-built drawings per building
  • Certification results for all 1,850 points
  • Witness test records
  • Access control configuration record
  • O&M manuals and labelling schedule